Compare contractor proposals on a common scope before choosing a builder. This Excel workbook shows how base bids, selected alternates, allowances, and scope differences can change the comparison.
Download a working copy and replace the sample project details, contractor information, prices, dates, scope selections, and review notes with your own project information. The sample figures are examples, not current market estimates or contractor offers. Complete the workbook in your spreadsheet application.
Adjusted Bid = Base Bid + Accepted Add Alternates − Accepted Deduct Alternates + Scope / Normalization Adjustment.
Replace every price input for each active bidder, entering 0 where no add, deduct, or scope adjustment applies. Partial entries can still produce an adjusted bid. For an unused bidder, clear all four price inputs in rows 14–17 so it does not remain in the lowest-bid comparison. Preserve the formula cells for Adjusted Bid and the variance rows.
Review the same scope item across all bidders, then request written clarification for exclusions and unclear assumptions. Check allowances against the selections and quantities you intend to use.
The comparison sheet also provides fields for proposed start, construction duration, warranty, insurance or bonding, license or registration, key exclusions, strengths, concerns, and overall notes. Replace the sample commentary rather than treating it as an assessment of your contractors.
Review these items alongside adjusted price before recording your decision. The lowest adjusted bid does not by itself confirm equivalent scope or contractor suitability. Keep the proposals and clarification correspondence with the completed workbook.
Use the Construction Budget Worksheet to track the broader project budget and the Project Planning Checklist to organize decisions before bidding and construction.